APPLICATION TIPS


*** For all the epoxy applications, dead times between layers can of course be utilized for other works, besides dead times can be minimized if different phases of the application take place in different parts of the project. Moreover, for bigger surfaces more square meters are possible per day in average because you will be able to work on bigger open surface with the same materials.

 

POLEPOX-DP 815


Application temperature:
10 to 35º C

Working temperature of applied material:
-5 to 50º C

Tools of application:
paint roller for 0.3-0.5 mm thickness-consumption (20-25º C): 0.2 kg/ m² on power-troweled industrial floors, in two layers-120 gr/ m²/first layer, 80 gr/ m²/second layer.
Time between layers of POLEPOX-DP 815: 5-8 hours

 

POLEPOX QUARTZ 849

Granulometry ~ 0.5 mm
Consumption (20-25º C): around 1.5 kg/ m² finally (after sweeping next day)
Covering after 12-15 hours
 

POLEPOX-DP 815
Application temperature:
10 to 35º C


Working temperature of applied material:
-5 to 50º C

Tools of application:

Single-rubber edge squeegee (and then press with mohair roller on top, for uniform dispersion/leveling out of the two-component dustproof epoxy impregnation resin POLEPOX-DP 815, in order not to cover the anti-slip effect of the grain of the sand)-consumption (20-25º C): 0.2-0.3 kg/ m², in three layers at least-120 gr/ m²/first layer on top of quartz sand, 80 gr/ m²/second layer, 50 gr/ m²/each additional layer.

Time between layers of POLEPOX-DP 815: 5-8 hours

For 1000m², 4 people will be needed for 6 days:

1st working day (8 hours): Grinding, cleaning, provisional sweeping, limited repairing with the two-component epoxy putty for horizontal surfaces EPOFIX-H 207 or the two-component epoxy putty, squeegee-applied EPOFIX S 214
2nd day: Final sweeping and first layer of POLEPOX-DP 815
3rd day: Second layer of POLEPOX-DP 815 and broadcasting of quartz sand
4th day: Sweeping of remaining quartz sand and application of the next POLEPOX-DP 815 layer
5th day: One more layer of POLEPOX-DP 815
6th day: One more layer of POLEPOX-DP 815

*Again, extensive repairing will affect times accordingly
*In all cases, the substrate is considered to be a decent power-troweled one.