APPLICATION TIPS


*** For all the epoxy applications, dead times between layers can of course be utilized for other works, besides dead times can be minimized if different phases of the application take place in different parts of the project. Moreover, for bigger surfaces more square meters are possible per day in average because you will be able to work on bigger open surface with the same materials.

 

POLEPOX-PR 826-W


Application temperature:
10 to 35º C

Working temperature of applied material:
-5 to 40º C

Tools of application:
Double-rubber edge squeegee for smooth concrete surfaces or brush for concrete surfaces in general

Consumption (20-25º C):
250-300 gr/m² on power-troweled industrial floors, in two layers at least (usually three or more), until the surface is saturated with primer, becoming glossy and gelly-less than 824 though.

Time between primer layers:
30-60 minutes

Covering of primer:
in 3-5 hours

 

POLEPOX FLOOR 828-CW

Application temperature:
10 to 30º C 

Working temperature of applied material:
-5 to 40º C

Tools of application:
Spotty roller with 4 mm spots for up to 2.0mm thickness in one layer -consumption (20-25º C): 4 kg/ m² (followed immediately by spiked roller over the surface to kill the air pockets and level out the surface)-or notched trowel with 4-5 mm notches in one layer

Covering of 828 with 814 or 817: after 3 days

POLEPOX COAT 827-W

Application temperature: 10 to 30º C

Working temperature of applied material: -5 to 40º C

Tools of application: Spotty roller with 2.1 mm spots for approx. 1 mm thickness in one layer -consumption (20-25º C): 1.5 kg/ m² (followed immediately by spiked roller over the surface to kill the air pockets and level out the surface) or paint roller for 0.8-1 mm thickness in two or more layers-consumption (20-25º C): approx. 1 kg/ m²


< back